SURFACE TRANSPORTATION BOARD DECISION DOCUMENT
    Decision Information

Docket Number:  
AB_369_7_X

Case Title:  
BUFFALO & PITTSBURGH RAILROAD, INC.-ABANDONMENT EXEMPTION-IN ERIE AND CATTARAUGUS COUNTIES, NY

Decision Type:  
Decision

Deciding Body:  
Director Of Proceedings

    Decision Summary

Decision Notes:  
DECISION GRANTED THE NYS OFFICE OF PARKS' REQUEST TO EXTEND THE NOTICE OF INTERIM TRAIL USE OR ABANDONMENT NEGOTIATING PERIOD TO APRIL 29, 2010.

    Decision Attachments

10 KB


Approximate download time at 28.8 kb: 19 Seconds

Note:
If you do not have Acrobat Reader, or if you have problems reading our files with your current version of Acrobat Reader, the latest version of Acrobat Reader is available free at www.adobe.com.

    Full Text of Decision

38616

40329                                    SERVICE DATE – OCTOBER 29, 2009

DO

 

SURFACE TRANSPORTATION BOARD

 

DECISION

 

STB Docket No. AB-369 (Sub-No. 7X)

 

BUFFALO & PITTSBURGH RAILROAD, INC.—ABANDONMENT EXEMPTION—IN ERIE AND CATTARAUGUS COUNTIES, NY

 

Decided:  October 28, 2009

 

Buffalo & Pittsburgh Railroad, Inc. (BPRR) filed a verified notice of exemption under 49 CFR 1152 Subpart F–Exempt Abandonments to abandon a 27.6‑mile line of railroad extending from milepost 8.4 in Orchard Park, in Erie County, NY, to milepost 36 in Ashford, in Cattaraugus County, NY.  Notice of the exemption was served and published in the Federal Register on October 6, 2008 (73 FR 58297).  In this decision, the Board is granting the request by the New York State Office of Parks, Recreation and Historic Preservation (NYS Office of Parks) to extend the interim trail use negotiation period.

 

By decision and notice of interim trail use or abandonment (NITU) served on November 4, 2008, the proceeding was reopened and a 180-day period was authorized for NYS Office of Parks to negotiate an interim trail use/rail banking agreement with BPRR for the right-of-way involved in this proceeding pursuant to the National Trails System Act, 16 U.S.C. 1247(d) (Trails Act).[1]  By a decision served on May 14, 2009, the trail use negotiation period under the NITU was extended until October 31, 2009.

 

By letter dated October 19, 2009, NYS Office of Parks has requested a 180-day extension of the NITU negotiating period to April 29, 2010.  In support, NYS Office of Parks states that the parties do not anticipate being able to consummate an agreement prior to the expiration date of the trail use negotiation period, but wish to continue negotiations.  By letter dated October 22, 2009, BPRR advises that it agrees to the extension as requested by NYS Office of Parks. 

 

Where, as here, the carrier is willing to continue trail use negotiations, the negotiating period may be extended.  An extension of the negotiating period will promote the establishment of trail use and rail banking consistent with the Trails Act. [2]  Accordingly, the NITU negotiating period will be extended for 180 days from October 31, 2009, to April 29, 2010.

 

            This decision will not significantly affect either the quality of the human environment or the conservation of energy resources.

 

            It is ordered:

 

            1.  The NYS Office of Parks’ request to extend the negotiation period is granted.

 

            2.  The negotiating period under the NITU is extended to April 29, 2010.

 

3.  This decision is effective on its service date.

 

By the Board, Joseph H. Dettmar, Acting Director, Office of Proceedings.

 

 

 

 

                                                                       

                                                                                                Anne K. Quinlan

                                                                                                Acting Secretary



[1]  In addition to interim trail use, the November 4, 2008 decision also imposed four environmental conditions and a public use condition that expired on May 4, 2009, and that may not be extended.  One of the environmental conditions was an historic preservation condition, which was removed by decision served on February 6, 2009.  The other three environmental conditions remain in effect.

 

 

[2]  See Rail Abandonments–Supplemental Trails Act Procedures, 4 I.C.C.2d 152, 157-58 (1987).