Docket Number:   | FD_33556_0 | ||
Case Title:   | CANADIAN NATIONAL RAILWAY COMPANY, GRAND TRUNK CORPORATION AND GRAND TRUNK WESTERN RAILROAD INCORPORATED--CONTROL--ILLINOIS CENTRAL CORPORATION, ILLINOIS CENTRAL RAILROAD COMPANY, CHICAGO, CENTRAL AND PACIFIC RAILROAD COMPANY, AND CEDAR RIVER RAILROAD COMPANY | ||
Decision Type:   | Decision | ||
Deciding Body:   | Secretary | ||
| Decision Summary | |||
Decision Notes:   | GRANTED IN PART, THE EMERGENCY EXTENSION REQUEST IN CN/IC-53 AND REVISED THE PROCEDURAL SCHEDULE AS SET FORTH IN THE APPENDIX TO THIS DECISION. | ||
| Decision Attachments | |||
| 10 KB | |||
| Approximate download time at 28.8 kb: 9 Seconds | |||
If you do not have Acrobat Reader, or if you have problems reading our files with your current version of Acrobat Reader, the latest version of Acrobat Reader is available free at www.adobe.com. | |||
| Full Text of Decision | |||
|
29825 SEC
This decision considers the emergency petition (designated as CN/IC-53) to modify the procedural schedule in this proceeding.(1) By petition filed November 30, 1998, applicants request
an extension of time of 5 business days from December 11, 1998, for applicants to file their
rebuttal and response to comments and requested conditions. Applicants refer to an
extraordinary circumstance as the reason for their extension request.
An extension of 5 calender days will be granted. Accordingly, the due date for
applicants' rebuttal and response to comments and requested conditions will be extended to
December 16, 1998. Rebuttal in support of inconsistent and responsive applications will be due
30 days later on January 15, 1999, instead of on January 11, 1999. The remainder of the
procedural schedule will not change.
It is ordered:
1. The emergency extension request in CN/IC-53 is granted in part, as discussed in this
decision. The due date for applicants' rebuttal and response to comments and requested
conditions is extended to December 16, 1998. The due date for rebuttal in support of
inconsistent and responsive applications is extended to January 15, 1999. The procedural
schedule, as revised, is set forth in the Appendix to this decision.
2. This decision is effective on the date of service.
By the Board, Vernon A. Williams, Secretary.
Vernon A. Williams Secretary December 16, 1998 Response to comments, protests, requested conditions, and other
opposition due. Response to comments of DOJ and DOT due. Rebuttal in
support of primary application and related application due. Response to
inconsistent and responsive applications due.
January 15, 1999 Rebuttal in support of inconsistent and responsive applications due.
February 19, 1999 Briefs due, all parties (not to exceed 50 pages for applicants and not to
exceed 25 pages for all other parties).
March 22, 1999 Oral argument (close of record).
March 29, 1999 Voting conference (at Board's discretion).
May 25, 1999 Date of service of final decision. 1. By application filed July 15, 1998, Canadian National Railway Company (CNR), Grand Trunk Corporation (GTC), and Grand Trunk Western Railroad Incorporated (GTW) (collectively with their affiliates, CN), Illinois Central Corporation (IC Corp.), Illinois Central Railroad Company (ICR), Chicago, Central and Pacific Railroad Company (CCP), and Cedar River Railroad Company (CRRC) (referred to collectively as IC) seek approval and authorization under 49 U.S.C. 11321-26 for: (1) the acquisition of control by CNR of IC Corp., ICR, and ICR's railroad affiliates; and (2) for the resulting common control by CNR of GTW and its railroad affiliates and ICR and its railroad affiliates. CN and IC are referred to collectively as applicants. | |||