| SURFACE TRANSPORTATION BOARD DECISION DOCUMENT | |||
| Decision Information | |||
Docket Number:   | AB_33_298_X | ||
Case Title:   | UNION PACIFIC RAILROAD COMPANY-ABANDONMENT EXEMPTION-IN FREEBORN COUNTY, MINN. | ||
Decision Type:   | Environmental Review | ||
Deciding Body:   | Director, Office Of Environmental Analysis | ||
| Decision Summary | |||
Decision Notes:   | CONCLUDED THAT THE ENVIRONMENTAL IMPACT STATEMENT PROCESS IS UNNECESSARY AND INVITED PUBLIC COMMENT. | ||
| Decision Attachments | |||
| 25 KB 24 KB 55 KB | |||
| Approximate download time at 28.8 kb: 49 Seconds | |||
If you do not have Acrobat Reader, or if you have problems reading our files with your current version of Acrobat Reader, the latest version of Acrobat Reader is available free at www.adobe.com. | |||
| Full Text of Decision | |||
|
41692 SERVICE DATE – JUNE 27, 2011 OEA SURFACE
TRANSPORTATION BOARD ENVIRONMENTAL
ASSESSMENT Docket
No. AB 33 (Sub-No. 298X) Union
Pacific Railroad Company – Abandonment Exemption – In Freeborn County, Minn. BACKGROUND In this proceeding, the Union Pacific Railroad Company (UP)
filed a notice under 49 C.F.R. § 1152.50 seeking exemption from the
requirements of 49 U.S.C. § 10903 to abandon a line of rail located in According to UP, the rail line proposed for abandonment was constructed in 1878 by the Minneapolis & St. Louis Railroad. UP indicates that its ownership of the line is mostly non-reversionary and that approximately 6 parcels totaling approximately 12.3 acres were acquired by an Act of Congress dated July 30, 1877. UP indicates that these parcels may have restrictions on the title that could affect the transfer or use of the land for other than railroad purposes. UP will make any relevant documentation in its possession concerning its ownership available to those requesting it. Following abandonment, UP believes that the right-of-way may be suitable for other public purposes including energy transmission, recreation, or conservation. UP believes that the right-of-way would not be suitable for use as a road or highway because the area is already well served. A majority of the rail line consists of 100-pound jointed rail installed in 1940 and 1942 and the right-of-way is generally 100 feet wide. The rail line travels through residential and rural areas and traverses Zip Codes 56007 and 56042. A map depicting the line in relationship to the area served is appended to this Environmental Assessment (EA). ENVIRONMENTAL REVIEW UP submitted an environmental report that concludes the quality of the human environment would not be affected significantly as a result of the abandonment or any post-abandonment activities, including salvage and disposition of the right-of-way. UP served the environmental report on a number of appropriate federal, state, and local agencies as required by the Surface Transportation Board’s (Board) environmental rules [49 C.F.R. § 1105.7(b)].[2] The Board’s Office of Environmental Analysis (OEA) has reviewed and investigated the record in this proceeding. Diversion of Traffic As noted above, UP states that no local traffic has moved over the line for at least 2 years and no overhead traffic would be rerouted. Accordingly, the proposed abandonment would not adversely impact the development, use and transportation of energy resources or recyclable commodities; transportation of ozone-depleting materials; or result in the diversion of rail traffic to truck traffic that could result in significant impacts to air quality or the local transportation network. Salvage Activities Impacts from salvage and disposal of a rail line typically include removal of tracks and ties, removal of ballast, dismantling of any bridges or other structures that may be present on the rail right-of-way, and regrading of the right-of-way. Salvage may be performed within the right-of-way, or, if necessary, via the construction of new access points to the right-of-way. UP has not provided a copy of its salvage procedure, therefore OEA is not certain if there would be any ground disturbance associated with salvage activities. However, OEA has included the U.S. Environmental Protection Agency and the U.S. Army Corps of Engineers in the service list for this proceeding so that they may comment on this EA. OEA believes that any air emissions associated with salvage operations would be temporary and would not have a significant impact on air quality. Noise associated with salvage activities would also be temporary and should not have a significant impact on the area surrounding the proposed abandonment. The proposed abandonment should not affect public safety because there has been no traffic on the rail line for at least 2 years. Freeborn County commented that it has an interest in providing
recreational trail opportunities and has recently filed a formal request for
public use and interim trails use for the entire right-of-way proposed for
abandonment. The U.S. Department of Commerce, National Geodetic Survey (NGS) commented
that there are 21 geodetic markers in the area of the proposed
abandonment. Therefore, OEA is
recommending a condition that requires UP
to notify NGS at least 90 days prior to
beginning salvage activities that will disturb or destroy any geodetic station
markers. The U.S. Army Corps of Engineers (USACE),
Rock Island District, commented that the proposed abandonment is not located
within its regulatory boundaries or jurisdiction. However, USACE noted that it has forwarded
information on the proposed abandonment to its St. Paul District for possible
comment. OEA has not heard back from the
St. Paul District but has included said office in the service list for this
proceeding and will include any comments it receives in the Final EA. Based on all information
available to date, OEA does not believe that salvage activities would cause
significant environmental impacts. In
addition to the parties on the Board’s service list for this proceeding, OEA is
providing a copy of this EA to the following agencies for review and
comment: U.S. Fish and Wildlife Service;
U.S. Department of Agriculture, Natural Resources Conservation Service; U.S.
Army Corps of Engineers; U.S. Environmental Protection Agency; the National
Geodetic Survey; National Park Service; Minnesota Environmental Protection
Agency; Minnesota Department of
Transportation; and the Freeborn County Commissioners. HISTORIC REVIEW UP served the historic report on
the Minnesota Historic Society (State Historic Preservation Office or SHPO)
pursuant to 49 CFR 1105.8(c). The SHPO has submitted comments stating that
the proposed abandonment would not affect any known historic properties listed
in or eligible for inclusion in the National Register of Historic Places
(National Register). We have reviewed
the report and the information provided by the SHPO and concur
with the SHPO’s comments. Pursuant to the
Advisory Council on Historic Preservation’s regulations for implementing the
Section 106 process of the National Historic Preservation Act at 36 CFR
800.5(c) and 36 CFR 800.8, we have determined that the proposed abandonment
will not adversely affect historic properties listed in or eligible for
inclusion in the National Register. The
documentation for this finding, as specified at 36 CFR 800.11(d), consists of
the railroad’s historic report, all relevant correspondence, and this EA, which
have been provided to the SHPO and made available to the public. Pursuant to 36 C.F.R. §
800.2, OEA conducted a search of the Native American Consultation Database to
identify federally-recognized tribes that may have ancestral connections to the
project area.[3] The database indicated that the following federally-recognized
tribes may have knowledge regarding properties of traditional religious and
cultural significance within the right-of-way (the APE) of the proposed
abandonment: the Flandreau Santee Sioux;
the Lower Sioux Indian Community Council; the Prairie Island Indian Community;
the Santee Sioux Nation; the Sisseton-Wahpeton Oyate
of the Lake Traverse Reservation; the Spirit Lake Tribal Council; and the Upper
Sioux Community of Minnesota.
Accordingly, OEA is sending a copy of this EA to those tribes for review
and comment. CONDITION We recommend that the
following condition be imposed on any decision granting abandonment authority: 1.
The
Union Pacific Railroad Company shall consult with the U.S. Department of
Commerce, National Geodetic Survey (NGS) and notify NGS at least 90 days prior
to beginning salvage activities that will disturb or destroy any geodetic
station markers. CONCLUSIONS Based on the information
provided from all sources to date, OEA concludes that, as currently proposed
and if the recommended mitigation is imposed, abandonment of the line will not
significantly affect the quality of the human environment. Therefore, the environmental impact statement
process is unnecessary. Alternatives to the
proposed abandonment would include denial (and therefore no change in
operations), discontinuance of service without abandonment, and continued
operation by another operator. In any of
these cases, the existing quality of the human environment and energy
consumption should not be affected. PUBLIC USE Following abandonment and salvage of the rail line, the right-of-way may be suitable for other public use. A request containing the requisite 4-part showing for imposition of a public use condition (49 C.F.R. § 1152.28) must be filed with the Board and served on the railroad within the time specified in the Federal Register notice. TRAILS USE A request for a notice of interim trail use (NITU) is due to the Board, with a copy to the railroad, within 10 days of publication of the notice of exemption in the Federal Register. Nevertheless, the Board will accept late-filed requests as long as it retains jurisdiction to do so in a particular case. This request must comply with the Board’s rules for use of rights-of-way as trails (49 C.F.R. § 1152.29). PUBLIC ASSISTANCE The Board’s Office of Public Assistance, Governmental Affairs, and Compliance (OPAGAC) responds to questions regarding interim trail use, public use, and other reuse alternatives. You may contact OPAGAC directly at (202) 245-0238, or mail inquiries to Surface Transportation Board, Office of Public Assistance, Governmental Affairs, and Compliance, Washington, DC 20423. COMMENTS If you wish to file comments regarding this Environmental Assessment, send an original and two copies to Surface Transportation Board, Case Control Unit, Washington, DC 20423, to the attention of Diana Wood, who prepared this Environmental Assessment. Environmental comments may also be filed electronically on the Board=s web site, www.stb.dot.gov, by clicking on
the “E-FILING” link. Please refer to
Docket No. AB 33 (Sub-No. 298X) in all correspondence, including e-filings, addressed to the Board. If you have any questions regarding this Environmental Assessment, please contact Diana Wood, the environmental contact for this case, by phone at (202) 245-0302, fax at (202) 245-0454, or e-mail at woodd@stb.dot.gov. Date made available to the public: June 27, 2011. Comment due date: July 13, 2011. By the Board, Victoria Rutson, Director, Office of Environmental Analysis.
Attachment [1] By decision served on June 2, 2009 in Docket AB 337 (Sub-No. 6X), the Board authorized the Dakota, Minnesota & Eastern Railroad to discontinue its trackage rights over the line proposed for abandonment. [2] The railroad’s environmental and historic reports are available for viewing on the Board’s website at www.stb.dot.gov by going to “E-Library,” selecting “Filings,” and then conducting a search for AB 33 (Sub-No. 298X). [3] Native American
Consultation Database, http://home.nps.gov/nacd/