Docket Number:   | AB_1086_0_X | ||
Case Title:   | PITTSBURGH & WEST VIRGINIA RAILROAD--ABANDOMENT EXEMPTION--IN ALLEGHENY COUNTY, PA. | ||
Decision Type:   | Environmental Review | ||
Deciding Body:   | Director, Office Of Environmental Analysis | ||
| Decision Summary | |||
Decision Notes:   | CONCLUDED THAT THE ENVIRONMENTAL IMPACT STATEMENT PROCESS IS UNNECESSARY AND INVITED PUBLIC COMMENT. | ||
| Decision Attachments | |||
| 39 KB 30 KB 1685 KB | |||
| Approximate download time at 28.8 kb: 8 Minutes | |||
If you do not have Acrobat Reader, or if you have problems reading our files with your current version of Acrobat Reader, the latest version of Acrobat Reader is available free at www.adobe.com. | |||
| Full Text of Decision | |||
|
41832 SERVICE DATE – SEPTEMBER 12, 2011 OEA SURFACE
TRANSPORTATION BOARD WASHINGTON, DC 20423 ENVIRONMENTAL
ASSESSMENT Docket
No. AB 1086X Pittsburgh
& West Virginia Railroad – Abandonment Exemption – In Allegheny County, Pa. Docket
No. AB 227 (Sub-No. 12X) Wheeling
& Lake Erie Railway Company – Discontinuance
of Service Exemption – In
Allegheny County, Pa. BACKGROUND In this proceeding, the Pittsburgh & West Virginia Railroad (PWV) and the Wheeling & Lake Erie Railway Company (WLE) (jointly Applicants) filed a notice under 49 C.F.R. § 1152.50 seeking exemption from the requirements of 49 U.S.C. § 10903 for PWV to abandon and WLE to discontinue its sublease rights[1] over a portion of railroad located in Allegheny County, Pennsylvania. The West End Branch (the line) extends from Milepost .58, near Green Tree, Pennsylvania to Milepost 2.4, near McKees Rocks, Pennsylvania, a distance of 1.82 miles. Applicants
certify that no rail cars have used the line for at least 2 years and that any
overhead traffic could be rerouted over other lines as a result of the
abandonment or discontinuance of sublease rights. Following abandonment, Applicants
indicate that the right-of-way may be used to support a Pennsylvania Department
of Transportation (PennDOT) roadway project – the West
End Improvement Project – which would improve vehicular traffic movement
through the west end of Pittsburgh by realigning, reconstructing and replacing road
and bridge infrastructure, retaining walls, drainage, guide rails, landscaping,
highway lighting, traffic signals, signing, and pavement markings. Based on information in the Applicants’ possession, the line does not contain any federally granted right-of-way. The right-of-way traverses U.S. Postal Service Zip Code 15220 and travels through urban land uses. Two maps depicting the line in relationship to the area served are appended to this Environmental Assessment (EA). If the notice becomes effective, PWV will be able to salvage track, ties, and other railroad appurtenances and to dispose of the right-of-way. ENVIRONMENTAL REVIEW Applicants submitted an environmental report that concludes the quality of the human environment would not be affected significantly as a result of the abandonment or any post-abandonment activities, including salvage and disposition of the right-of-way. Applicants served the environmental report on a number of appropriate federal, state, and local agencies as required by the Surface Transportation Board’s (Board) environmental rules [49 C.F.R. § 1105.7(b)].[2] The Board’s Office of Environmental Analysis (OEA) has reviewed and investigated the record in this proceeding.
Diversion of Traffic Applicants state that no local traffic has moved over the line for at least 2 years and no overhead traffic would be rerouted. Accordingly, the proposed abandonment and discontinuance would not adversely impact the development, use and transportation of energy resources or recyclable commodities; transportation of ozone-depleting materials; or result in the diversion of rail traffic to truck traffic that could result in significant impacts to air quality or the local transportation network. Salvage Activities Impacts
from salvage and disposal of a rail line typically include removal of tracks
and ties, removal of ballast, dismantling of any bridges or other structures
that may be present on the rail right-of-way, and regarding of the
right-of-way. Salvage may be performed
within the right-of-way, or if necessary, via construction of new access points
to the right-of-way. If the Board should
approve this abandonment and discontinuance, PWV would salvage the rail, ties
and track material, and remove the overhead structures along the right-of-way
in support of the previously discussed PennDOT road
improvement project. PWV does not
anticipate any impacts on waterways, wetlands, or floodplain during salvage,
and further indicates that any disturbance to the ground should be minimal. OEA believes that any air emissions associated with salvage operations would be temporary and would not have a significant impact on air quality. Noise associated with salvage activities would also be temporary and should not have a significant impact on the area surrounding the proposed abandonment. PennDOT,
working with the U.S. Department of Transportation’s Federal Highway Administration,
previously assessed the environmental impacts of the planned roadway
improvement project. Consequently, PennDOT raised no concerns regarding the potential
environmental impacts of the proposed abandonment. The U.S. Army Corps of Engineers (Corps) commented that it has jurisdiction over all waters of the United States, and that discharges of dredged or fill materials into these waters, including wetlands, requires prior authorization from the Corps under Section 404 of the Clean Water Act (33 U.S.C. §1344). It further stated that a permit may be required for the proposed abandonment, should there be such discharges. To ensure compliance with its regulations, OEA is recommending a condition that would require PWV to consult with the Corps prior to initiating salvage of the rail line, and that it comply with the Corps’ reasonable requirements. The Pennsylvania Department of Environmental Protection (PADEP), Southwest Regional Office, provided a comment letter that lists a number of issue areas that may be of concern during salvage operations. Specifically, PADEP notes that permits and/or additional reviews may be required if salvage activities associated with the proposed abandonment generate demolition waste; fugitive dust; contaminated soil; watershed disturbances; erosion and sedimentation; wastewater discharges; or concrete waste discharge. Further reviews would also be required if there are any associated water tanks, oil and gas wells, or water wells in the area of the proposed abandonment, or if there is a need to develop emergency response contingency plans. PADEP indicates that its Southwest Regional Office would coordinate the internal reviews to ensure efficient use of its resources. OEA is therefore recommending a condition that requires PWV to consult with PADEP’s Southwest Regional Office prior to conducting salvage operations to determine what, if any, permits are needed prior to the salvage process. The Allegheny County, Department of Public Works (DPW) commented that it has no facilities in the right-of-way of the proposed abandonment, and therefore no issues, and that it supports PennDOT’s efforts to improve traffic circulation through the west end of Pittsburgh. Based on all information
available to date, OEA does not believe that salvage activities would cause
significant environmental impacts. In
addition to the parties on the Board’s service list for this proceeding, OEA is
providing a copy of this EA to the following agencies for review and
comment: the U.S. Fish and Wildlife
Service; the U.S. Environmental Protection Agency; the U.S. Army Corps of
Engineers; the U.S. Natural Resources Conservation Service; the National Park
Service; the National Geodetic Survey; the Pennsylvania Department of
Transportation; the Pennsylvania Department of Environmental Protection; the
Pennsylvania Historical and Museum Commission; the Allegheny County Department
of Public Works; and the Pennsylvania Department of Health. HISTORIC REVIEW Applicants
served the historic report on the Pennsylvania Historical and Museum
Commission, Bureau for Historic Preservation (State Historic Preservation
Office or SHPO), pursuant to 49 C.F.R. § 1105.8(c). The
SHPO has submitted comments stating that the proposed abandonment and discontinuance
of service would not affect any known historic properties listed in or eligible
for inclusion in the National Register of Historic Places (National
Register). We have reviewed the report
and the information provided by the SHPO and concur
with the SHPO’s comments. Pursuant to the Advisory Council on Historic
Preservation’s regulations for implementing the Section 106 process of the
National Historic Preservation Act at 36 C.F.R. § 800.5(c) and 36 C.F.R. §
800.8, we have determined that the proposed abandonment would not adversely
affect historic properties listed in or eligible for inclusion in the National
Register. The documentation for this
finding, as specified at 36 C.F.R. § 800.11(d), consists of the railroad’s Historic Report, all relevant
correspondence, and this EA, which have been provided to the SHPO and made
available to the public. Pursuant to 36 C.F.R. § 800.2, OEA conducted
a search of the Native American Consultation Database to identify any
federally recognized tribes that may have ancestral connections to the project.[3] The
database indicated that there are no federally recognized tribes that may have knowledge
regarding properties of traditional religious and cultural significance within
the right-of-way (the Area of Potential Effect). CONDITIONS We recommend that the following conditions be
imposed on any decision granting abandonment authority: 1. Prior to commencement of any salvage activities, the Pittsburgh & West Virginia Railroad (PWV) shall consult with the U.S. Army Corps of Engineers (Corps) regarding potential impacts to waters of the United States, including wetlands, and shall comply with the reasonable requirements of the Corps. 2. Prior to commencement of any salvage activities, PWV shall consult with the Pennsylvania Department of Environmental Protection, Southwest Regional Office, to ensure that any concerns in the right-of-way are addressed regarding demolition waste; fugitive dust; contaminated soil; watershed disturbances; erosion and sedimentation; wastewater discharges; concrete waste discharge; water tanks; oil and gas wells; water wells; and emergency response contingency plans. CONCLUSIONS Based on the information provided from all sources to date, OEA concludes that, as currently proposed and if the recommended mitigation is imposed, abandonment of the line will not significantly affect the quality of the human environment. Therefore, the environmental impact statement process is unnecessary. Alternatives to the proposed abandonment would include denial (and therefore no change in operations), discontinuance of service without abandonment, and continued operation by another operator. In any of these cases, the existing quality of the human environment and energy consumption should not be affected. PUBLIC USE Following abandonment and salvage of the rail line, the right-of-way may be suitable for other public use. A request containing the requisite 4-part showing for imposition of a public use condition (49 C.F.R. § 1152.28) must be filed with the Board and served on the railroad within the time specified in the Federal Register notice. TRAILS USE A request for a notice of interim trail use (NITU) is due to the Board, with a copy to the railroad, within 10 days of publication of the notice of exemption in the Federal Register. Nevertheless, the Board will accept late-filed requests as long as it retains jurisdiction to do so in a particular case. This request must comply with the Board’s rules for use of rights-of-way as trails (49 C.F.R. § 1152.29). PUBLIC ASSISTANCE The Board’s Office of Public Assistance, Governmental Affairs, and Compliance (OPAGAC) responds to questions regarding interim trail use, public use, and other reuse alternatives. You may contact OPAGAC directly at (202) 245-0238, or mail inquiries to Surface Transportation Board, Office of Public Assistance, Governmental Affairs, and Compliance, Washington, DC 20423. COMMENTS If you wish to file comments regarding this Environmental Assessment, send an original and two copies to Surface Transportation Board, Case Control Unit, Washington, DC 20423, to the attention of Diana Wood, who prepared this Environmental Assessment. Environmental comments may also be filed electronically on the Board=s web site, www.stb.dot.gov, by clicking on
the “E-FILING” link. Please refer to
Docket No. AB 1086X in all correspondence, including e-filings, addressed to the Board. If you have any questions regarding this Environmental Assessment, please contact Diana Wood, the environmental contact for this case, by phone at (202) 245-0302, fax at (202) 245-0454, or e-mail at woodd@stb.dot.gov. Date made available to the public: September 12, 2011. Comment due date: September 27, 2011. By the Board, Victoria Rutson, Director, Office of Environmental Analysis.
Attachment
[1] WLE acquired
its sublease rights to perform local and common carrier service from Norfolk
and Western Railway Company pursuant to a 1990 agreement. Finance Docket 31591, Wheeling Acquisition
Corp. – Acquisition and Operation Exemption – Lines of Norfolk & W. Ry. Co.
(ICC served May 7, 1990). [2] The Environmental and Historic Reports are
available for viewing on the Board’s website at www.stb.dot.gov by going to “E-Library,” selecting “Filings,” and
then conducting a search for AB 1086 (Sub-No. 0X). [3] Native American Consultation Database, http://home.nps.gov/nacd/ (last visited August 25, 2011). | |||