Docket Number:   | AB_33_289_X | ||
Case Title:   | UNION PACIFIC RAILROAD COMPANY-ABANDONMENT EXEMPTION-IN PULASKI COUNTY, ARK. | ||
Decision Type:   | Environmental Review | ||
Deciding Body:   | Chief Of Section Of Environmental Analysis | ||
| Decision Summary | |||
Decision Notes:   | CONCLUDED THAT THE ENVIRONMENTAL IMPACT STATEMENT PROCESS IS UNNECESSARY AND INVITED PUBLIC COMMENT. | ||
| Decision Attachments | |||
| 25 KB 826 KB | |||
| Approximate download time at 28.8 kb: 4 Minutes | |||
If you do not have Acrobat Reader, or if you have problems reading our files with your current version of Acrobat Reader, the latest version of Acrobat Reader is available free at www.adobe.com. | |||
| Full Text of Decision | |||
|
41152 SERVICE DATE – OCTOBER 26, 2010 OEA SURFACE
TRANSPORTATION BOARD WASHINGTON, DC 20423 ENVIRONMENTAL ASSESSMENT Docket
No. AB 33 (Sub-No. 289X) Union
Pacific Railroad Company – Abandonment Exemption – in Pulaski County, Ark. BACKGROUND In this
proceeding, Union Pacific Railroad Company (UP) filed a notice of exemption
under 49 C.F.R. § 1152.50 seeking exemption from the requirements of 49 U.S.C.
§ 10903 in connection with the abandonment of a portion of a rail line, known
as the Camp Robinson Spur, in Pulaski County, Arkansas. The rail line proposed for abandonment
extends approximately 4.04 miles from milepost 345.64 near Levy, to milepost
349.68 near DESCRIPTION OF THE LINE According
to UP, the Missouri Pacific Railroad constructed the Line to Camp Pike (later
renamed Camp Joseph T. Robinson) in 1917.
The track currently consists of a mixture of 75 and 85 pound jointed and
welded rail. The Line crosses under
Interstate 40 and proceeds northeastward through a relatively level residential
and commercial area. It then curves
westward and enters a forested and hilly area before terminating at a row of
warehouses at ENVIRONMENTAL REVIEW UP submitted an Environmental Report that concludes the quality of the human environment would not be affected significantly as a result of the abandonment or any post-abandonment activities, including salvage and disposition of the right-of-way. UP served the Environmental Report on a number of appropriate federal, state, and local agencies as required by the Surface Transportation Board’s (Board) environmental rules [49 C.F.R. § 1105.7(b)].[1] The Board’s Office of Environmental Analysis (OEA)[2] has reviewed and investigated the record in this proceeding. Diversion of Traffic According to UP, no local traffic has moved over the Line for at least 2 years, and there is no overhead traffic to be rerouted. Accordingly, the proposed abandonment would not adversely impact the development, use and transportation of energy resources or recyclable commodities; transportation of ozone-depleting materials; or result in the diversion of rail traffic to truck traffic that could result in significant impacts to air quality or the local transportation network. Salvage Activities Impacts from salvage and disposal
of a rail line typically include removal of tracks and ties, removal of
ballast, dismantling of any bridges or other structures that may be present on
the rail right-of-way, and regrading of the right-of-way. Salvage may be performed within the
right-of-way, or, if necessary, via the construction of new access points to
the right-of-way. OEA notes that UP is
also currently seeking to abandon a .32-mile portion of rail line, known as the
Junction Bridge Line, in The U.S. Army Corps of Engineers (Corps) submitted comments stating that it has authorized the proposed abandonment under the Department of Army Nationwide Permit (NWP) process. Specifically, the proposed abandonment is authorized by four (4) NWPs, provided that certain conditions are met. One of these conditions requires that UP submit compliance certification within 30 days of completion of the project. Accordingly, we recommend that UP consult with the Corps regarding the required NWP conditions and comply with the Corps’ reasonable requirements. The National
Geodetic Survey (NGS) identified one geodetic station marker in the area of the
proposed abandonment. Accordingly, OEA recommends a condition that
requires UP to consult with NGS and notify NGS at least 90 days prior to
beginning salvage activities that would disturb or destroy the geodetic station
marker. The U.S. Environmental Protection Agency’s Region 6 Office (USEPA) has not submitted comments regarding the proposed abandonment. Accordingly, OEA will provide a copy of this EA to USEPA for its review and comment. Based on all information available to date, OEA does not believe that salvage activities would cause significant environmental impacts. In addition to the parties on the Board’s service list for this proceeding, OEA is providing a copy of this EA to the Corps and USEPA for their review and comment. HISTORIC REVIEW UP served the Historic Report on
the Arkansas Historic Preservation Program (State Historic Preservation Office
or SHPO), pursuant to 49 C.F.R. § 1105.8(c).
Based on available information,
the SHPO has submitted comments stating that no known historic properties
listed in or eligible for inclusion in the National Register of Historic Places
(National Register) would be affected by the proposed abandonment. Accordingly, pursuant to the Section 106 regulations of the National
Historic Preservation Act at 36 C.F.R. § 800.4(d)(1), and following
consultation with the SHPO and the public, we have determined that the
proposed abandonment would not affect historic properties listed in or eligible
for inclusion in the National Register.
The documentation for this finding, as specified at 36 C.F.R. § 800.11(d),
consists of the railroad’s Historic Report, all relevant correspondence, and
this EA, which have been provided to the SHPO and made available to the public through posting on the Board’s website
at http://www.stb.dot.gov. Pursuant to 36 C.F.R. § 800.2, OEA conducted
a search of the Native American Consultation Database at http://home.nps.gov/nacd/
to identify federally-recognized tribes which may have ancestral connections to
the project area. The database indicated that the Osage Tribe, CUMULATIVE IMPACTS As noted above, UP filed
a notice of exemption with the Board seeking to abandon another portion of rail
line in The regulations of the Council on Environmental Quality implementing the National Environmental Policy Act (NEPA) at 42 U.S.C. §§ 4321-43, define a cumulative impact as “the impact on the environment, which results from the incremental consequences of an action when added to other past, present, and reasonably foreseeable future actions, regardless of what agency or person undertakes such other actions.” (40 C.F.R. § 1508.7). This ensures that the range of actions that are considered in the NEPA document includes not only the project proposed, but also all actions that could contribute to cumulative impacts.
OEA received comments similar to those described above for
the proposed abandonment of the .32-mile segment in CONDITIONS We recommend that the following conditions be
imposed on any decision granting abandonment authority:
CONCLUSIONS Based
on the information provided from all sources to date, OEA concludes that, as
currently proposed, and if the recommended conditions are imposed, abandonment
of the Line will not significantly affect the quality of the human
environment. Therefore, the
environmental impact statement process is unnecessary. Alternatives to the proposed abandonment would include denial (and therefore no change in operations), discontinuance of service without abandonment, and continued operation by another operator. In any of these cases, the existing quality of the human environment and energy consumption should not be affected. PUBLIC USE Following abandonment and salvage of the rail line, the right-of-way may be suitable for other public use. A request containing the requisite 4-part showing for imposition of a public use condition (49 C.F.R. § 1152.28) must be filed with the Board and served on the railroad within the time specified in the Federal Register notice. TRAILS USE A request for a notice of interim trail use (NITU) is due to the Board, with a copy to the railroad, within 10 days of publication of the notice of exemption in the Federal Register. Nevertheless, the Board will accept late-filed requests as long as it retains jurisdiction to do so in a particular case. This request must comply with the Board’s rules for use of rights-of-way as trails (49 C.F.R. § 1152.29). PUBLIC ASSISTANCE The Board’s Office of Public Assistance, Governmental
Affairs, and Compliance responds to questions regarding interim trail use,
public use, and other reuse alternatives.
You may contact this office directly at (202) 245-0238, or mail
inquiries to Surface Transportation Board, Office of Public Assistance,
Governmental Affairs, and Compliance, COMMENTS If you
wish to file comments regarding this Environmental Assessment, send an original
and 2 copies to Surface Transportation Board, Case Control Unit, Date made available to the public: October 26, 2010. Comment due date: November 9, 2010. By the Board, Victoria Rutson, Director, Office of Environmental Analysis. Attachment [1] The
Environmental and Historic Reports are available for viewing on the Board’s
website at www.stb.dot.gov by going
to “E-Library,” selecting “Filings,” and then conducting a search for AB 33
(Sub-No. 289X). [2] OEA was formerly known as the Board’s Section of Environmental Analysis (SEA). The name change from SEA to OEA became effective on September 1, 2010. [3] Materials filed in that proceeding can be
viewed on the Board’s website at www.stb.dot.gov
by going to “E-Library,” selecting “Filings,” and then conducting a search for
AB 33 (Sub-No. 290X). | |||