    Decision Summary

Decision Notes:  
DECISION GRANTED A REQUEST TO REVISE THE PROCEDURAL SCHEDULE IN THIS PROCEEDING.

    Decision Attachments

8 KB
15 KB
21 KB

Approximate download time at 28.8 kb: 21 Seconds

Note:
If you do not have Acrobat Reader, or if you have problems reading our files with your current version of Acrobat Reader, the latest version of Acrobat Reader is available free at www.adobe.com.

    Full Text of Decision

41638                        SERVICE DATE – LATE RELEASE MAY 18, 2011

DO

SURFACE TRANSPORTATION BOARD

 

DECISION

 

Docket No. EP 558 (Sub-No. 14)

 

RAILROAD COST OF CAPITAL—2010

 

Decided:  May 18, 2011

 

            This decision grants a request to revise the procedural schedule in this proceeding.

 

            By a request filed on May 17, 2011, the Western Coal Traffic League (WCTL) seeks an extension of the procedural schedule established by the Board in a decision served on February 22, 2011.  WCTL seeks to extend the filing deadline for statements of other interested parties from May 19, 2011, to June 2, 2011.  WCTL also requests an extension of time for rebuttal statements by the railroads, changing the deadline from June 8, 2011, to June 22, 2011.  WCTL states that the Association of American Railroads has advised WCTL that it does not oppose this extension request.   

 

            WCTL seeks this extension for three reasons:  (1) a staff member of the consulting firm that WCTL employs for cost-of-capital matters unexpectedly passed away on Thursday, May 12, 2011; (2) the procedural schedule established by the Board in this proceeding provides 20 days for reply statements, which is less than the period of time allocated in past cost-of-capital proceedings; and (3) an extension of nine to eleven days would cause comments to be due during the Memorial Day Holiday. 

 

            WCTL’s request to extend the procedural schedule will be granted.  The deadlines proposed by WCTL for the remainder of this proceeding will be adopted.

 

It is ordered:

 

            1.  WCTL’s request to revise the procedural schedule is granted.

 

            2.  Statements of other interested persons are due by June 2, 2011.  Rebuttal statements by the railroads are due by June 22, 2011.

 

            3.  This decision is effective on its date of service.

 

            By the Board, Rachel D. Campbell, Director, Office of Proceedings.