| SURFACE TRANSPORTATION BOARD DECISION DOCUMENT | |||
| Decision Information | |||
Docket Number:   | AB_33_262_X | ||
Case Title:   | UNION PACIFIC RAILROAD COMPANY--ABANDONMENT EXEMPTION--IN FULTON AND PEORIA COUNTIES, ILL. | ||
Decision Type:   | Decision | ||
Deciding Body:   | Director Of Proceedings | ||
| Decision Summary | |||
Decision Notes:   | DECISION GRANTED ILLINOIS DEPARTMENT OF NATURAL RESOURCES REQUEST TO EXTEND THE NOTICE OF INTERIM TRAIL USE NEGOTIATING PERIOD UNTIL NOVEMBER 13, 2011. | ||
| Decision Attachments | |||
| 10 KB 21 KB 28 KB | |||
| Approximate download time at 28.8 kb: 28 Seconds | |||
If you do not have Acrobat Reader, or if you have problems reading our files with your current version of Acrobat Reader, the latest version of Acrobat Reader is available free at www.adobe.com. | |||
| Full Text of Decision | |||
|
41684 SERVICE DATE – JUNE 20, 2011 DO SURFACE TRANSPORTATION BOARD DECISION Docket No. AB 33 (Sub-No. 262X) UNION PACIFIC RAILROAD COMPANY–ABANDONMENT EXEMPTION– IN
FULTON AND PEORIA COUNTIES, ILL. Decided: June 17, 2011 Union Pacific Railroad Company (UP)
filed a notice of exemption under 49 C.F.R. pt. 1152 subpart F—Exempt
Abandonments to abandon a 24.7-mile line of railroad on UP’s Elm Industrial
Lead from milepost 461.5, near Middle Grove, to milepost 486.2, at Molitor Junction, in Fulton and Peoria Counties, Ill. Notice of the exemption was served on July
23, 2008, and published in the Federal Register on July 28, 2008 (73 Fed.
Reg. 43,823).
By decision and notice of interim trail use or abandonment (NITU) served
on November 13, 2008, the proceeding was reopened and a 180-day period was authorized for the Illinois Department
of Natural Resources (IDNR) to negotiate an interim trail use/rail banking
agreement with UP for the right-of-way involved in this proceeding. By a series of decisions issued from May 11,
2009, to December 14, 2010, the NITU negotiating period was extended until May
13, 2011. On April 19, 2011, IDNR filed a letter requesting an extension of the NITU negotiating period until November 13, 2011.[1] IDNR states that it continues to work with local partner jurisdictions to compile specific information in an effort to satisfy its negotiating needs, and it has been in direct contact with UP, but it does not believe that the parties will be able to finalize negotiations during the current negotiating period. By letter filed on June 6, 2011, UP consents to IDNR’s request to extend the NITU negotiating period until November 13, 2011. Where, as here, the carrier has not consummated the abandonment at the end of the previously imposed negotiating period and is willing to continue trail use negotiations, the Board retains jurisdiction, and the NITU negotiating period may be extended.[2] Under the circumstances, further extension of the negotiating period is warranted. See Birt v. STB, 90 F.3d 580, 588-90 (D.C. Cir. 1996); Grantwood Vill. v. Mo. Pac. R.R., 95 F.3d 654, 659 (8th Cir. 1996). Accordingly, the NITU negotiating period will be extended to November 13, 2011. This decision will not significantly affect either the quality of the human environment or the conservation of energy resources. It is ordered: 1. IDNR’s request to extend the NITU negotiating period is granted. 2. The negotiating period under the NITU is extended until November 13, 2011. 3. This decision is effective on its service date. By the Board, Rachel D. Campbell, Director, Office of Proceedings. [1] Although the
request exceeds the customary request of 180 days (until November 9, 2011), the
Board has granted such requests in the past.
See e.g., S. Pac. Transp. Co. —Aband. Exemption—Wendel-Alturas
Line in Modoc and Lassen Counties, Cal. AB 12 (Sub-No. 184X) (STB served
Sept. 1, 2005). [2] See Rail
Aban.—Use of Rights-of-Way as Trails—Supplemental
Trails Act Procedures, 4 I.C.C.2d 152, 157-58 (1987). | |||